Request for Proposal (RFP) for the Procurement of Software Support Maintenance for OpenText Application Lifecycle Management (ALM) and Unified Functional Testing (UFT) for Bank Negara Malaysia

18 Nov 2026

Bank Negara Malaysia (BNM) invites qualified and experienced suppliers who fulfil the requirements listed below to participate in the above-mentioned tender.

Mandatory Requirements

Only suppliers who meet the following mandatory requirements will be considered for this tender.

No.

Mandatory requirements

Documents required
(in PDF format)

1.

Malaysia registered business and has local presence for ALM and UFT service support.

 

Companies Commission of Malaysia Certificate for Business Registration.

Local office address which provides the ALM UFT supports to the BNM.

2.

The company agrees to strictly maintain the confidentiality of all information received from BNM and provide a letter of undertaking on confidentiality, signed by the company’s authorised representative(s)

Signed Letter of Undertaking on Confidentiality.

3.

(i)   The company and/or its senior management/directors/shareholders have not been subject to any criminal or civil investigations in the last five (5) years

(ii)   A declaration must be provided for any litigation or disputes (past and ongoing cases) instituted against the company and/or its management, directors or shareholders (if applicable)

 

Note: Automatic disqualification if the company and/or its shareholders/directors/ senior management are:

(a)     convicted of any criminal offence relating to dishonesty, fraud, obstruction of crime prevention efforts, drug trafficking or immigration under any written law or law of any country; or

(b)     listed in the anti-money laundering (AML)/sanction list issued by Kementerian Dalam Negeri (KDN) or United Nations Security Council Resolutions (UNSCR)

Signed Statutory Declaration of all Litigation and Dispute (past and ongoing case) that has been instituted against the company and/or its management/directors/ shareholders (if any).

 

4.

An authorised partner/reseller for ALM and UFT from Product Principal [Gold/Platinum level].

 

Letter of authorised partner/reseller from Product Principal Open Text, confirming the supplier's Gold/Platinum partner status for ALM and UFT.

 

Scope of Work

The scope of work for the Procurement of Software Support Maintenance for Opentext Application Lifecycle Management (ALM) and Unified Functional Testing (UFT) is as follows (details are provided in the RFP):

  • Renewal and support maintenance for thirty-five (35) OpenText ALM licences and thirty-five (35) OpenText UFT licences for a period of two (2) years;

  • Provision of software updates, upgrades, patches, fixes, and version releases throughout the contract period;

  • Provision of technical support, troubleshooting, and issue resolution services;

  • Ensuring uninterrupted access to ALM and UFT testing functionalities;

  • Provision of qualified local technical resources and support services; and

  • Provision of fixed pricing for any optional additional licences, services, or plugins related to OpenText ALM and UFT during the contract period.

Tender Process Milestones

 A summary of the timeline of the tender process is as follows:

Activity

Start date

End date

Suppliers onboarding process into the Digital Operations Platform (DOP)

20 November 2026

 27 November 2026

RFP document issuance

4 December 2026

-

Tender briefing

8 December 2026

-

Tender closing date/time

-

22 December 2026

 

Issuance of Tender Documents

Only suppliers registered in the Supplier Portal (Link: BNM Supplier Portal) and meeting the above mandatory requirements will be considered for this tender. For any further clarification regarding registration, please email to [email protected] or contact +603 2784 5397 / 5613 / 5346 (Supplier Management).

Upon registration, please email [email protected] to express your intention to participate in the tender (Subject: Procurement of Software Support Maintenance for OpenText Application Lifecycle Management (ALM) and Unified Functional Testing (UFT) for Bank Negara Malaysia).

The tender documents will be accessible via BNM Supplier Portal starting from the RFP document issuance date. New suppliers are required to download the Supplier Registration Guide to complete the registration process. Existing suppliers can log in directly.

BNM disclaims all liability for tender documents not received by suppliers. Only suppliers who have registered in BNM Supplier Portal and meet the mandatory requirements will be eligible to participate in the tender exercise.

Submission of Completed Tender Document

All submissions must be completed online. Suppliers are required to submit duly completed proposals via the BNM Supplier Portal by logging in no later than 5:00 p.m., 22 December 2026. BNM will not be held responsible for any delays in tender submissions and no submissions will be accepted outside the portal.

For general enquiries related to pre-tendering, please email [email protected].However, any enquiries specific to this tender should be submitted via the BNM Supplier Portal (Messaging) at the respective tender/negotiation ID.

Disclaimer

  • BNM shall not be responsible for any delay in the submission of any tender proposals nor loss of the related documents should they be submitted through any other means than that stipulated by BNM.

  • Proof of posting shall not be accepted as evidence of the supplier’s submission of proposal. BNM will also not be responsible for any cost incurred by the suppliers in relation to their participation in this tender exercise.

  • BNM reserves the right to only consider quotations/proposals/documents that are fully completed and submitted on or before the date and time as specified above. Late responses will not be entertained. BNM is not bound to accept the lowest bid or any tender and reserves the right to reject all tenders.